CHAPTER 4 : CASE STUDIES OF ALTERNATIVE QUALITY MANAGEMENT 4.1 Introduction Previous chapters focused on the historic and current state of quality management practice and identified the most common quality management models in use in the highway industry. The focus of this chapter is on the ten case studies conducted by the research team and the relevant analyses and observations of those case studies.
|
From page 90... ...
rigor. Recognizing this common criticism, the authors sought to generate a defensible, repeatable method to guide the case study process.
|
From page 91... ...
effort. Because participants received no compensation for their time by the research team, it was essential to make contact with participants who expressed enthusiasm about assisting with the research effort and was in a position to coordinate with the rest of the participants on the project.
|
From page 92... ...
Table 4-1 – List of Case Studies P – Pilot case study The primary criterion for case study selection was that the projects under consideration utilize some form of alternative quality management. While the range of possible alternative quality management procedures leads is long, this one requirement greatly limits the number of potential case studies as most projects still utilize the baseline delivery and quality management methods.
|
From page 93... ...
Figure 4-1 – Geographic Dispersion of Case Studies After all the criteria were considered, 10 suitable projects were identified and used as case studies. As mentioned above, one of the most important aspects of all the projects was identification of a champion for the research effort.
|
From page 94... ...
quality management system used on the project and any notable features of that system. The graphic included with each summary is the QAO diagram for that project.
|
From page 95... ...
Project Acceptance Construction Quality Assurance Design Quality Assurance Design Quality Control Construction Quality Control Design Released for Construction Construction Released for Final Payment Quality Assurance Constructor's Responsibility Designer's Responsibility Independent Assurance (if req'd) - functional audit -physical audit WSDOT's Design Staff Responsiblity WSDOT's Construction Staff Responsibility Independent Assurance (if req'd)
|
From page 96... ...
Quality Management Responsibility Allocation: A summary of design and construction QM roles is shown in table 4-2. Table 4-2 – Summary of design and construction QM roles Responsibility allocation for design management tasks Agency Design Staff Agency PM Staff Design Consultant Staff Constructor's Pre-const.
|
From page 97... ...
4.5.2 Willamette River Bridge, Oregon Project Name: Willamette River Bridge Name of Agency: Oregon Department of Transportation (ODOT) Location: I-5 over the Willamette River in Lane County at the border of the cities of Eugene and Springfield, OR.
|
From page 98... ...
QAO: Figure 4-3 shows that the QAO for this project was Deterministic. Project Acceptance Construction Quality Assurance Design Quality Assurance Design Quality Control Construction Quality Control Design Released for Construction Construction Released for Final Payment Independent Assurance (if req'd)
|
From page 99... ...
Quality Management Responsibility Allocation: A summary of design and construction QM roles is shown in table 4-3. Table 4-3 – Summary of design and construction QM roles Responsibility allocation for design management tasks Agency Design Staff Agency PM Staff Design Consultant Staff Constructor's Pre-const.
|
From page 100... ...
Effective QM Practices: Early contractor involvement in the design process Flexibility afforded by CMGC method Allowing contractor to use competitive bidding OR negotiated contracts for subcontractors 4.5.3 Portland Transit Mall Revitalization, Oregon Project Name: Portland Transit Mall (Greenline) Revitalization Name of Agency: Tri-County Metropolitan Transportation District or Oregon (TriMet)
|
From page 101... ...
QAO: Figure 4-4 shows that the QAO for this project was Deterministic. Project Acceptance Construction Quality Assurance Design Quality Assurance Design Quality Control Construction Quality Control Design Released for Construction Construction Released for Final Payment Independent Assurance (if req'd)
|
From page 102... ...
Quality Management Responsibility Allocation: A summary of design and construction QM roles is shown in table 4-4. Table 4-4 – Summary of design and construction QM roles Responsibility allocation for design management tasks Agency Design Staff Agency PM Staff Design Consultant Staff Constructor's Pre-const.
|
From page 103... ...
Effective QM Practices: Contractor involvement early in the design process Electronic recording and submission of daily reports Allowing contractor utilize own inspectors for QC and materials testing Use of CMGC delivery method 4.5.4 Tuttle Creek Dam Safety Assurance Project, Kansas Project Name: Tuttle Creek Dam Safety Assurance Project Name of Agency: US Army Corps of Engineers (USACE) Location: Tuttle Creek, north of the City of Manhattan in Kansas, along the Big Blue River Project Delivery Method/Procurement/Contract Type: Corps Early Contractor Involvement (ECI)
|
From page 104... ...
QAO: Figure 4-5 shows that the QAO for this project was Deterministic. Project Acceptance Construction Quality Assurance Design Quality Assurance Design Quality Control Construction Quality Control Design Released for Construction Construction Released for Final Payment Quality Assurance Constructor's Responsibility Designer's Responsibility Independent Assurance (if req'd)
|
From page 105... ...
Quality Management Responsibility Allocation: A summary of design and construction QM roles is shown in table 4-5. Table 4-5 – Summary of design and construction QM roles Responsibility allocation for design management tasks Agency personnel Consultant design staff Constructor's preconstructi on staff Agency-hired QA/oversight consultant Technical review of design deliverables ✔ ✔ ✔ Checking of design calculations ✔ Checking of quantities ✔ ✔ Acceptance of design deliverables ✔ ✔ ✔ Review of specifications ✔ ✔ ✔ Approval of final construction plans & other design documents ✔ ✔ Approval of progress payments for design progress ✔ Approval of post-award design QM/QA/QC plans ✔ Responsibility allocation for construction management tasks Agency personnel Consultant design staff Constructor's construction staff Agency-hired QA/oversight consultant Technical review of construction shop drawings ✔ ✔ Technical review of construction material submittals ✔ ✔ Checking of pay quantities ✔ Routine construction inspection ✔ Quality control testing ✔ Verification testing ✔ Acceptance testing ✔ Approval of progress payments for construction progress Approval of construction post-award QM/QA/QC plans Report of nonconforming work or punch list.
|
From page 106... ...
Interdisciplinary checks - Interdisciplinary coordination is a key element of the QCP. The checks are usually conducted by the design team members who check each other's work to assure compatibility.
|
From page 107... ...
QAO: Figure 4-6 shows that the QAO for this project was Assurance. Project Acceptance Construction Quality Assurance Design Quality Assurance Design Quality Control Construction Quality Control Design Released for Construction Construction Released for Final Payment Independent Assurance (if req'd)
|
From page 108... ...
Quality Management Responsibility Allocation: A summary of design and construction QM roles is shown in table 4-6. Table 4-6 – Summary of design and construction QM roles Responsibility allocation for design management tasks Agency personnel Consultant design staff Constructor's preconstruction staff Agency-hired QA/oversight consultant Technical review of design deliverables ✔ ✔ ✔ Checking of design calculations ✔ Checking of quantities ✔ ✔ Acceptance of design deliverables ✔ Review of specifications ✔ ✔ ✔ Approval of final construction plans & other design documents ✔ Approval of progress payments for design progress ✔ Approval of post-award design QM/QA/QC plans ✔ Responsibility allocation for construction management tasks Agency personnel Consultant design staff Constructor's construction staff Agency-hired QA/oversight consultant Technical review of construction shop drawings ✔ ✔ Technical review of construction material submittals ✔ ✔ Checking of pay quantities ✔ ✔ Routine construction inspection ✔ ✔ Quality control testing ✔ Verification testing ✔ ✔ Acceptance testing ✔ Approval of progress payments for construction progress ✔ Approval of construction post-award QM/QA/QC plans ✔ ✔ Report of nonconforming work or punch list.
|
From page 109... ...
Goal-Setting Session - The Contractor was required to participate in an initial goal-setting session with UDOT 4.5.6 U.S. 160 4th Lane Addition, Colorado Project Name: U.S.
|
From page 110... ...
QAO: Figure 4-7 shows that the QAO for this project was Oversight. Project Acceptance Construction Quality Assurance Design Quality Assurance Design Quality Control Construction Quality Control Design Released for Construction Construction Released for Final Payment Owner Verification (if req'd)
|
From page 111... ...
Quality Management Responsibility Allocation: Table 4-7 shows a summary of design and construction QM roles. Table 4-7 – Summary of design and construction QM roles Responsibility allocation for design management tasks Agency personnel Consultant design staff Constructor's preconstruction staff Agency-hired QA/oversight consultant Technical review of design deliverables ✔ ✔ Checking of design calculations ✔ Checking of quantities ✔ ✔ ✔ Acceptance of design deliverables ✔ Review of specifications ✔ Approval of final construction plans & other design documents ✔ Approval of progress payments for design progress ✔ Approval of post-award design QM/QA/QC plans ✔ Responsibility allocation for construction management tasks Agency personnel Consultant design staff Constructor's construction staff Agency-hired QA/oversight consultant Technical review of construction shop drawings ✔ ✔ Technical review of construction material submittals ✔ ✔ Checking of pay quantities ✔ Routine construction inspection ✔ Quality control testing ✔ Verification testing ✔ ✔ Acceptance testing ✔ Approval of progress payments for construction progress ✔ Approval of construction post-award QM/QA/QC plans ✔ Report of nonconforming work or punchlist.
|
From page 112... ...
Location: I-15, 500 North to I-215, Utah Project Delivery Method/Procurement/Contract Type: DB/Best-Value/Lump Sum Project Description: The project consists of the reconstruction of Interstate 15 from 500 North in Salt Lake City to the I-215 overpass in Davis County. The project includes the design, reconstruction, and widening of the mainline highway to include an Express Lane and three general purpose lanes in each direction.
|
From page 113... ...
QAO: Figure 4-8 shows that the QAO for this project was Oversight. Project Acceptance Construction Quality Assurance Design Quality Assurance Design Quality Control Construction Quality Control Design Released for Construction Construction Released for Final Payment Independent Assurance (if req'd)
|
From page 114... ...
Quality Management Responsibility Allocation: A summary of design and construction QM roles is shown in table 4-8. Table 4-8 – Summary of design and construction QM roles Responsibility allocation for design management tasks Agency personnel Consultant design staff Constructor's preconstruction staff Agency-hired QA/oversight consultant Technical review of design deliverables ✔ ✔ ✔ Checking of design calculations ✔ Checking of quantities ✔ Acceptance of design deliverables ✔ Review of specifications ✔ ✔ ✔ Approval of final construction plans & other design documents ✔ Approval of progress payments for design progress ✔ Approval of post-award design QM/QA/QC plans ✔ Responsibility allocation for construction management tasks Agency personnel Consultant design staff Constructor's construction staff Agency-hired QA/oversight consultant Technical review of construction shop drawings ✔ Technical review of construction material submittals ✔ Checking of pay quantities ✔ Routine construction inspection ✔ Quality control testing ✔ Verification testing ✔ Acceptance testing ✔ Approval of progress payments for construction progress ✔ Approval of construction post-award QM/QA/QC plans ✔ Report of nonconforming work or punchlist.
|
From page 115... ...
Summary of Innovation and Enhanced Quality - The Proposers were to prepare a summary of no more than three pages that outlined the specific areas in which the Proposer had introduced innovation and provided enhanced quality in long-term performance, durability, or maintainability. Document Control - The QMP had to specify procedures for meeting documentation requirements, for document control and for the specific responsibilities of personnel to satisfy these requirements.
|
From page 116... ...
QAO: Figure 4-9 shows that the QAO for this project was Oversight. Project Acceptance Construction Quality Assurance Design Quality Assurance Design Quality Control Construction Quality Control Design Released for Construction Construction Released for Final Payment Independent Assurance (if req'd)
|
From page 117... ...
Quality Management Responsibility Allocation: A summary of design and construction QM roles is shown in table 4-9. Table 4-9 – Summary of design and construction QM roles Responsibility allocation for design management tasks Agency personnel Consultant design staff Constructor's preconstruction staff Agency-hired QA/oversight consultant Technical review of design deliverables ✔ ✔ Checking of design calculations ✔ Checking of quantities ✔ Acceptance of design deliverables ✔ Review of specifications ✔ Approval of final construction plans & other design documents ✔ Approval of progress payments for design progress ✔ Approval of post-award design QM/QA/QC plans ✔ Responsibility allocation for construction management tasks Agency personnel Consultant design staff Constructor's construction staff Agency-hired QA/oversight consultant Technical review of construction shop drawings ✔ ✔ Technical review of construction material submittals ✔ Checking of pay quantities Routine construction inspection ✔ ✔ Quality control testing ✔ Verification testing ✔ Acceptance testing ✔ Approval of progress payments for construction progress ✔ Approval of construction post-award QM/QA/QC plans ✔ Report of nonconforming work or punchlist.
|
From page 118... ...
Quality Oversight Visits - During the design process, MnDOT could make oversight visits to discuss and verify design progress and ascertain the overall progress of the Project with respect to the Contractor's Quality Manual. Disincentive - Subject to MnDOT's determination, MnDOT could assess the Contractor a $100-per-hour monetary deduction for failure to facilitate satisfactory progress or completion of the Work.
|
From page 119... ...
QAO: Figure 4-10 shows that the QAO for this project was Acceptance. Project Acceptance Construction Quality Assurance Design Quality Assurance Design Quality Control Construction Quality Control Design Released for Construction Construction Released for Final Payment Independent Assurance (if req'd)
|
From page 120... ...
Quality Management Responsibility Allocation Summary For this case study independent questionnaires were received from the design builder (D) , the concessionaire (C)
|
From page 121... ...
Effective QM Practices: The dual Construction Engineer Inspection process where there is an oversight CEI (OCEI) hired by the agency and a CEI hired by the concessionaire (CCEI)
|
From page 122... ...
components: the Quality Control (QC) Program, the Owner Oversight Program, the Independent Assurance (IA)
|
From page 123... ...
Quality Management Responsibility Allocation: A summary of design and construction QM roles is shown in table 4-11. Table 4-11 – Summary of design and construction QM roles Responsibility allocation for design management tasks Agency personnel Consultant design staff Constructor's preconstruction staff Agency-hired QA/oversight consultant Technical review of design deliverables ✓ ✓ Checking of design calculations ✓ ✓ Checking of quantities ✓ ✓ Acceptance of design deliverables ✓ ✓ Review of specifications ✓ Approval of final construction plans & other design documents ✓ ✓ Approval of progress payments for design progress ✓ Approval of post-award design QM/QA/QC plans ✓ Responsibility allocation for construction management tasks Agency personnel Consultant design staff Constructor's construction staff Agency-hired QA/oversight consultant Technical review of construction shop drawings ✓ Technical review of construction material submittals ✓ Checking of pay quantities ✓ Routine construction inspection ✓ ✓ Quality control testing ✓ Verification testing ✓ ✓ Acceptance testing ✓ Approval of progress payments for construction progress ✓ Approval of construction post-award QM/QA/QC plans ✓ ✓ Report of nonconforming work or punchlist.
|
From page 124... ...
developed to process material testing data and to transmit them electronically to TxDOT for statistical validation. To meet the project needs, ELVIS was further expanded to support CQAF construction inspection reporting and manage pavement surface ride quality.
|
From page 125... ...
found in the Assurance QAO, this was not found in the case studies examined. Similarly, while a project using DBB delivery could potentially allow the contractor to assume a quality assurance role as found in an Assurance QAO, the baseline QAO and the one used on the WSDOT project studied was the Deterministic QAO.
|
From page 126... ...
Table 4-13 – Summary of Varying Quality Roles Quality Management Roles and Responsibilities # QAO Project Acceptance Design QC Design QA Const. QC Const.
|
From page 127... ...
Table 4-14 – Summary of Required pre-Award Submittals Required Proposal/Bid Package Submittals Case Study Number 1 2 3 4 5 6 7 8 9 10 Qualifications of Design Quality Manager ✔+ ✔+ ✔+ ✔+ ✔+ ✔+ Qualifications of Construction Quality Manager ✔ ✔+ ✔+ ✔+ ✔+ Qualifications of other QM personnel ✔+ ✔+ ✔+ ✔+ ✔+ ✔+ Design quality management plan ✔+ ✔+ ✔+ ✔+ ✔+ Design criteria checklists ✔+ ✔+ ✔+ ✔+ Construction quality management/control plan ✔+ ✔+ ✔+ Construction testing matrix ✔+ ✔ Quality-based incentive/disincentive features ✔+ ✔ Warranties ✔ ✔ ✔+ +: Evaluated to make award decision(s) Four case studies required submission of one of these documents or less before making award decisions.
|
From page 128... ...
Table 4-15 – List of Emerging Alternative QM Tools Pre-award Tools Post-award Tools Owner led o Pre-bid meeting with focus on quality o Industry review of draft RFP with focus on quality o ISO 9000 certification for organization, project, or team member o Alternative QM approaches in procurement o Quality based selection of contractors/subcontractors (projectspecific prequalification) o Use of warranties (performance or materials)
|