Suggested Citation:"Appendix F: High-Risk Items Within the Risk and Opportunity Analysis Report." National Academies of Sciences, Engineering, and Medicine. 2020. Review of the Department of Energy's Plans for Disposal of Surplus Plutonium in the Waste Isolation Pilot Plant. Washington, DC: The National Academies Press. doi: 10.17226/25593.
×

Appendix F

High-Risk Items Within the Risk and Opportunity Analysis Report

INTRODUCTION

The Risk and Opportunity Analysis Report (ROAR) (SRNS, 2018a) provides analyses by the Department of Energy’s National Nuclear Security Administration (DOE-NNSA) of cost and schedule risks for the proposed dilute and dispose plan. Some risks may need continuous review as details of designs for the proposed facilities, equipment, processes, and operations are developed in preparation for a program Conceptual Design at stages CD-1 (approved in late 2019) and the start of construction activities after CD-3A approval (approved in early 2020, DOE-NNSA, 2018).

This committee has not reviewed the underlying operations data used by DOE-NNSA to conduct the ROAR and Life-Cycle Cost Estimate (LCCE) evaluations (SRNS, 2018a,b). That is, the committee did not independently verify the stated frequency of realized risks such as unplanned process excursions, equipment breakdowns, or accidents that were used by DOE-NNSA to determine programmatic risks to cost and schedule. The U.S. Army Corps of Engineers’ review also did not investigate the underlying operations data. The operations data are based on experience at the sites or models developed in the course of the various dilute and dispose activities and trial runs to date.

Pantex’s role is to provide 26.2 metric tons (MT) of pit material in classified amounts in a licensed Type B package under a classified schedule to the Los Alamos National Laboratory (LANL). This step is unchanged from the previous plan to dispose of surplus plutonium using irradiated mixed oxide fuel. Currently the FL-type Type B container is certified for transportation from Pantex; for the dilute and dispose plan, a new MD-2 container is expected to be certified and used (Whitworth, 2018). See Figure F-1.

Image
FIGURE F-1 MD-2 Type B container: (a) photo of the new MD-2 container, (b) cross section of the MD-2 container. The MD-2 containers, designed to be stronger and have improved ceramic insulation over the existing FL containers, were developed to support shipment of surplus pits for the Surplus Plutonium Disposition (SPD) Program in fiscal year (FY) 2021. SOURCE: Cantey and Robertson, 2019. Images provided by the Department of Energy.
Suggested Citation:"Appendix F: High-Risk Items Within the Risk and Opportunity Analysis Report." National Academies of Sciences, Engineering, and Medicine. 2020. Review of the Department of Energy's Plans for Disposal of Surplus Plutonium in the Waste Isolation Pilot Plant. Washington, DC: The National Academies Press. doi: 10.17226/25593.
×

DOE-NNSA plans to qualify and build the MD-2 container, which is stronger than the FL package and has an improved ceramic insulation formulation to pass drop and burn tests. The new MD-2 enables the pits to be kept in current sealed containers and is expected to be ready for use in FY 2021. In terms of Technology Readiness Level (TRL) the MD-2 is listed as TRL-7 (Cantey and Robertson, 2019) and should be able to come online well ahead of the time that it is needed for dilute and dispose operations ramp-up in 2023. Other plans related to improved containers for LANL operations are outlined in Box F-1.

ROAR REVIEW

The ROAR document identifies risks for the dilute and dispose program ranked low, moderate, and high. The ROAR also identifies a number of opportunities to offset the risks. Below, we provide an overview of the high risks and opportunities for the program.

Suggested Citation:"Appendix F: High-Risk Items Within the Risk and Opportunity Analysis Report." National Academies of Sciences, Engineering, and Medicine. 2020. Review of the Department of Energy's Plans for Disposal of Surplus Plutonium in the Waste Isolation Pilot Plant. Washington, DC: The National Academies Press. doi: 10.17226/25593.
×

Los Alamos National Laboratory

There are several scale-up risks for operations at LANL that are ranked as high risk to program schedule and cost.1 These have to do with both equipment and operations:

  • Anomalous events causing delays. These are unforeseen and known to occur; this is a matter of normal contingency planning. Such events must be accepted and accounted for in the program plan. Process upsets often result in major shutdowns. Background documentation for the program does not indicate how much time is built into the schedule for such anomalous events, although the ROAR does say that serious events can disrupt production for 1 year or more, stopping activity downstream at SRS and the Waste Isolation Pilot Plant. The documentation does not specify the nature of potential anomalous events.
  • Equipment installation schedule delays. The program plan calls for efforts to mitigate this risk, presumably during the ramp-up phase of the program.

___________________

1 In October 2019, the U.S. Government Accountability Office issued a report that examined DOE’s capacity to produce plutonium oxide as DOE-NNSA begins to plan an expanded capability to produce pits (GAO, 2019).

Suggested Citation:"Appendix F: High-Risk Items Within the Risk and Opportunity Analysis Report." National Academies of Sciences, Engineering, and Medicine. 2020. Review of the Department of Energy's Plans for Disposal of Surplus Plutonium in the Waste Isolation Pilot Plant. Washington, DC: The National Academies Press. doi: 10.17226/25593.
×
  • Inability to use a SAVY container for storing and shipping oxide product to SRS. The committee assumes that is a schedule risk but not a scale-up risk. That is, use of the 3013 instead of the SAVY container may slow down the operations, thus diminishing concerns about scale-up but extending program completion beyond the 2049-2056 time frame.
  • Lower than planned oxide production rate. The ROAR document says that this can be mitigated at a cost of $150 million. Although the ROAR does not specify it, the committee assumes that these funds would be applied to increase the number of lines and/or shifts. The committee notes that the needed oxide production rate is much greater than previously demonstrated, a significant risk as noted in the ROAR.
  • Productivity impact of insufficient storage. The ROAR document says this can be avoided for $10 million.

The opportunities to offset scale-up risks at LANL are

  • Install additional capacity at a cost of $67 million. There is no detail as to how much schedule improvement would result with this expenditure.
  • Share with other installations at LANL in the proximity of the dilute and dispose operations.
  • Maximize production prior to and/or during facility modifications. This can be achieved for $22.3 million, according to the document.
  • Perform small in-line sample analysis. An additional expenditure of $3.5 million is assumed by DOE-NNSA to facilitate the process throughout.

Savannah River Site

The ROAR document (SRNS, 2018a) identifies two risks at SRS that are ranked as high risk to program schedule and cost. These have to do with both equipment and operations:

  • Failure of characterization equipment. The plans are to perform non-destructive assay (NDA), real-time radiography (RTR), and flammable gas analysis (FGA) without standby equipment. To mitigate this risk, the costs of purchasing spare NDA, RTR, and FGA equipment are included in the LCCE baseline.
  • Delay in K Area operations. Savannah River Nuclear Solutions may not complete the necessary steps allowing K Area operation to begin. Even with mitigation efforts this risk remains high.

The ROAR document also identifies a number of SRS scale-up risks ranked as moderate or low in terms of cost and schedule and identifies a number of opportunities to offset risks at SRS:

  • Increase criticality control overpack (CCO) loading. Increasing the loading of a CCO from 300 g Pu to 330 g Pu would decrease glovebox labor and reduce the number of containers, amount of container handling and storage, and the number of shipments. However, it would demand high-accuracy measurements in K Area with unacceptable third-party entrance into K Area. Therefore, this opportunity is deemed of low probability of success.
  • Optimize storage requirements. Among the SRS requirements for ensuring safe storage of nuclear material in K Area are multiple mass measurements of incoming fissile materials for criticality analysis. Work is in progress to eliminate these multiple measurements at LANL by using multiple scales and independent verification, which would reduce cost and personnel exposure at LANL.
Suggested Citation:"Appendix F: High-Risk Items Within the Risk and Opportunity Analysis Report." National Academies of Sciences, Engineering, and Medicine. 2020. Review of the Department of Energy's Plans for Disposal of Surplus Plutonium in the Waste Isolation Pilot Plant. Washington, DC: The National Academies Press. doi: 10.17226/25593.
×
  • Streamline waste tracking methods. Current waste characterization processes are designed for differing small-quantity wastes and necessitate significant effort. However, the dilute and dispose waste is uniform, and a streamlined waste tracking process in E Area is possible, leading to significant cost savings.
  • Treat E Area facility as contamination free. Currently five or more radiological surveys are made when CCOs are moved before shipping. There is a potential to eliminate many of these surveys to be reflected in cost savings.

REFERENCES

Cantey, T., and S. Robertson. 2019. Surplus Plutonium Disposition Program Container Utilization. SRNS‐MS‐201900071. Aiken, SC: Savannah River Nuclear Solutions.

DOE-NNSA (Department of Energy’s National Nuclear Security Administration). 2018. Surplus Pu Disposition Master Summary Schedule, June. Provided to the committee by DOE-NNSA (accessed March 8, 2020).

GAO (Government Accountability Office). 2019. Surplus Plutonium Disposition: NNSA’s Long-Term Plutonium Oxide Production Plans Are Uncertain. GAO-20-166. https://www.gao.gov/assets/710/702239.pdf (accessed March 8, 2020).

SRNS (Savannah River Nuclear Solutions). 2018a. Risk and Opportunity Management Plan for the National Nuclear Security Administration Surplus Plutonium Disposition Program Dilute and Dispose Approach. Y-RMP-G-00023, Rev. 1, February. Aiken, SC: SRNS.

SRNS. 2018b. Surplus Plutonium Disposition Program Dilute and Dispose Approach Life Cycle Cost Estimate, Summary Report. SRNS-RP-2018-00570, Rev. 0, May. Aiken, SC: SRNS.

SRNS. 2018c. Surplus Plutonium Disposition Technical Baseline Description for the Proposed Dilute and Dispose Approach. SRNS-TR-2016-00285, Rev. 1, June. Aiken, SC: SRNS.

Stone, T. 2012. Los Alamos National Laboratory Overview of the SAVY-4000 Design: Meeting the Challenge for Worker Safety. LA-UR-12-01729. Presented at Fifty-Third Annual Meeting of the Institute of Nuclear Materials Management. https://permalink.lanl.gov/object/tr?what=info:lanl-repo/lareport/LA-UR-12-01729 (accessed March 31, 2020).

Whitworth, J. 2018. “ARIES Oxide Production Program Dilute and Dispose LCCE Overview, Material Management and Minimization Program,” LA-UR- 18-28648, Independent Validation Review, August 28–30, 2018. https://permalink.lanl.gov/object/tr?what=info:lanl-repo/lareport/LA-UR-18-28648 (accessed March 22, 2020).

Suggested Citation:"Appendix F: High-Risk Items Within the Risk and Opportunity Analysis Report." National Academies of Sciences, Engineering, and Medicine. 2020. Review of the Department of Energy's Plans for Disposal of Surplus Plutonium in the Waste Isolation Pilot Plant. Washington, DC: The National Academies Press. doi: 10.17226/25593.
×
Page 145
Suggested Citation:"Appendix F: High-Risk Items Within the Risk and Opportunity Analysis Report." National Academies of Sciences, Engineering, and Medicine. 2020. Review of the Department of Energy's Plans for Disposal of Surplus Plutonium in the Waste Isolation Pilot Plant. Washington, DC: The National Academies Press. doi: 10.17226/25593.
×
Page 146
Suggested Citation:"Appendix F: High-Risk Items Within the Risk and Opportunity Analysis Report." National Academies of Sciences, Engineering, and Medicine. 2020. Review of the Department of Energy's Plans for Disposal of Surplus Plutonium in the Waste Isolation Pilot Plant. Washington, DC: The National Academies Press. doi: 10.17226/25593.
×
Page 147
Suggested Citation:"Appendix F: High-Risk Items Within the Risk and Opportunity Analysis Report." National Academies of Sciences, Engineering, and Medicine. 2020. Review of the Department of Energy's Plans for Disposal of Surplus Plutonium in the Waste Isolation Pilot Plant. Washington, DC: The National Academies Press. doi: 10.17226/25593.
×
Page 148
Suggested Citation:"Appendix F: High-Risk Items Within the Risk and Opportunity Analysis Report." National Academies of Sciences, Engineering, and Medicine. 2020. Review of the Department of Energy's Plans for Disposal of Surplus Plutonium in the Waste Isolation Pilot Plant. Washington, DC: The National Academies Press. doi: 10.17226/25593.
×
Page 149
Next: Appendix G: Acronyms and Abbreviations »
Review of the Department of Energy's Plans for Disposal of Surplus Plutonium in the Waste Isolation Pilot Plant Get This Book
×
 Review of the Department of Energy's Plans for Disposal of Surplus Plutonium in the Waste Isolation Pilot Plant
Buy Paperback | $75.00 Buy Ebook | $59.99
MyNAP members save 10% online.
Login or Register to save!
Download Free PDF

In 2018, the National Academies of Sciences, Engineering, and Medicine issued an Interim Report evaluating the general viability of the U.S. Department of Energy's National Nuclear Security Administration's (DOE-NNSA's) conceptual plans for disposing of 34 metric tons (MT) of surplus plutonium in the Waste Isolation Pilot Plant (WIPP), a deep geologic repository near Carlsbad, New Mexico. It provided a preliminary assessment of the general viability of DOE-NNSA's conceptual plans, focused on some of the barriers to their implementation. This final report addresses the remaining issues and echoes the recommendations from the interim study.

READ FREE ONLINE

  1. ×

    Welcome to OpenBook!

    You're looking at OpenBook, NAP.edu's online reading room since 1999. Based on feedback from you, our users, we've made some improvements that make it easier than ever to read thousands of publications on our website.

    Do you want to take a quick tour of the OpenBook's features?

    No Thanks Take a Tour »
  2. ×

    Show this book's table of contents, where you can jump to any chapter by name.

    « Back Next »
  3. ×

    ...or use these buttons to go back to the previous chapter or skip to the next one.

    « Back Next »
  4. ×

    Jump up to the previous page or down to the next one. Also, you can type in a page number and press Enter to go directly to that page in the book.

    « Back Next »
  5. ×

    Switch between the Original Pages, where you can read the report as it appeared in print, and Text Pages for the web version, where you can highlight and search the text.

    « Back Next »
  6. ×

    To search the entire text of this book, type in your search term here and press Enter.

    « Back Next »
  7. ×

    Share a link to this book page on your preferred social network or via email.

    « Back Next »
  8. ×

    View our suggested citation for this chapter.

    « Back Next »
  9. ×

    Ready to take your reading offline? Click here to buy this book in print or download it as a free PDF, if available.

    « Back Next »
Stay Connected!