... January 3, 2005. Final Report External Independent Review of the Building 431 Demolition; Approve Performance Baseline/Start Field Work (CD-2/3)
From page 40...
... August 2004. Corrective Action Plan, Limited External Independent Review of the Highly Enriched Uranium Materials Facility Project Appendix C
From page 41...
... July 08, 2004. External Independent Review Fundamental Neutron Physics Beamline Project Approve Performance Baseline CD-2, Final Report.
From page 42...
... External Independent Review of Glass Waste Storage Building #2, Approve Performance Baseline/Approve Start of Construction Review CD-2/3. Depleted Uranium Hexafluoride 6 (DUF6 )
From page 43...
... EM Cleanup Project Lifecycle Baseline External Independent Review Corrective Action Plan; Recommended Path Forward to Close Out Responses to Findings.