Skip to main content

Currently Skimming:


Pages 87-92

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 87...
... should be repeated for each project delivery method that survives the Tier 2 process. Due to cost escalation on large transit projects, since 2002, the FTA has required that each "New Starts" project undergo a formal risk-based cost estimate.
From page 88...
... If a project goes into the Final Design Phase without a decision on a project delivery method, the agency will lose the opportunity to effectively use alternative delivery methods and will be limited to the traditional DBB approach. At the end of the Conceptual Design Phase, the agency usually has not done a detailed risk analysis.
From page 89...
... Risk factors are rated, always from the perspective of the owner agency, according to the effect of a particular project delivery method on that risk factor. In the hypothetical case shown in Table 6.1, from the agency perspective, DBB is seen as having a favorable effect on the risk factor of "permits/approvals." The agency thinks that it is the best party to obtain permits/approvals and that it can most effectively do this using a DBB approach.
From page 90...
... If this risk analysis is not a requirement (for example in projects that do not apply for federal funding) , then it is suggested that the proj90 A Guidebook for the Evaluation of Project Delivery Methods Risk Analysis Cost/Schedule - Ranked Risk Factors - Risk Factor 1 - Risk Factor 2 … Quantitative Approach (See Fig.
From page 91...
... However, the choice of the project delivery method is a natural outcome of a risk analysis exercise because one of the most important benefits of any risk analysis is risk allocation/mitigation. A properly selected project delivery method is an effective risk mitigation instrument that can help keep project costs low and minimize project delays.
From page 92...
... Both analyses are based on a risk-allocation exercise that will determine major risks to the agency under various project delivery methods. In the qualitative approach, the decision-makers carefully examine each risk factor and deliberate the anticipated effect of each risk factor on project cost and schedule.


This material may be derived from roughly machine-read images, and so is provided only to facilitate research.
More information on Chapter Skim is available.