Skip to main content

Currently Skimming:


Pages 72-88

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 72...
... CHAPTER 3 : QUALITY ASSURANCE ORGANIZATIONS 3.1 Introduction Quality Assurance Organizations (QAOs) in the highway industry have been evolving since the 1960s.
From page 73...
... 3.3 Quality Assurance Organization (QAO) Presentation Each QAO is graphically represented using the generic QAO framework, shown in Figure 3-1.
From page 74...
... 3.4 Fundamental Highway QAOs The five fundamental QAOs for the highway construction and design industry identified by this research are listed below:  Deterministic – The traditional approach to quality within the highway industry. The agency retains all project quality roles, responsibilities and activities.
From page 75...
... the ability to build quality into the final product beginning at the design stage instead of inspecting it at a later stage. (Desai and Mital 2009)
From page 76...
... Project Acceptance Construction Acceptance Design Acceptance Design Quality Control Construction Quality Control Design Released for Construction Construction Released for Final Payment Quality Assurance Designer's Responsibility Owner's Responsibility Constructor's Responsibility Owner's Responsibility Independent Assurance (if req'd) - functional audit -physical audit Independent Assurance (if req'd)
From page 77...
... applied to CMGC if the scope of preconstruction work for the contractor was limited to items not directly relating to the design: cost estimates and project scheduling. In contrast, the Deterministic QAO is not well suited for a DB project.
From page 78...
... Figure 3-4 graphically depicts the Assurance QAO as applied to a dual contract project (separate contracts for the designer and the contractor)
From page 79...
... Another variation on the Assurance QAO used DB projects is the shared variation. This variation shares the responsibilities for design acceptance and construction acceptance between the owner and the design builder, shown in Figure 3-6.
From page 80...
... Project Acceptance Construction Acceptance Design Acceptance Design Quality Control Construction Quality Control Design Released for Construction Construction Released for Final Payment Independent Assurance (if req'd) - functional audit -physical audit Quality Assurance Independent Assurance (if req'd)
From page 81...
... resources must then be focused on the quality requirements within the contract not on the detailed technical details of the project. While the variation in Figure 3-8 results in a proactive approach to construction quality, it results in a reactive approach to design quality by the agency maintaining control of the design acceptance function.
From page 82...
... Design Quality Control Construction Quality Control Construction Acceptance Design Acceptance Design Builder's Responsibility Figure 3-9 – Variable QAO, agency has complete design quality responsibility The Variable QAO construction assurance variation has been implemented on Design-Build projects as shown in Figure 3-7. Currently there are no examples from the data showing that the design assurance variation is in use in the industry.
From page 83...
... Project Acceptance Construction Acceptance Design Acceptance Design Quality Control Construction Quality Control Design Released for Construction Construction Released for Final Payment Independent Assurance (if req'd) - functional audit -physical audit Quality Assurance Independent Assurance (if req'd)
From page 84...
... to learn how to perform this function. While the agency always ultimately has the risk for quality on a project, in the Oversight QAO, quality risk shifts to the designer and the contractor.
From page 85...
... for design, construction, operations, and maintenance, there is a shift in financial liabilities, which also pertains to the shift of the quality responsibilities (Gransberg et al.
From page 86...
... is hired jointly by the concessionaire and the agency to perform not only owner verification testing but also independent assurance and any other quality acceptance activities that are now part of the concessionaire's responsibility, but the agency pays for 100% of owner verification testing. Notice that even the decision of accepting design for construction and accepting construction for final payment is a responsibility of the concessionaire due to the financial liability of the concessionaire to correct any design or construction deficiencies during the operations and maintenance period (Gransberg et al.
From page 87...
... Table 3-1 – Roles and responsibilities of the five fundamental QAOs Quality Assurance Organization Design Acceptance Design QC Construction Acceptance Construction QC Deterministic Agency Agency Agency Contractor Assurance Agency Designer Agency Contractor Variable Designer Designer Agency Contractor Oversight Designer Designer Contractor Contractor Acceptance Concessionaire Concessionaire Concessionaire Concessionaire Further investigation of each of the organizations was conducted to identify the approach to quality, the level of owner control, and the delivery methods for which it is applicable. The approach to quality was expressed as reactive, heavily focused on final product inspections; or proactive, building quality into the process.
From page 88...
... During the reduction process there were some common traits/factors observed among all of the QAO models.

Key Terms



This material may be derived from roughly machine-read images, and so is provided only to facilitate research.
More information on Chapter Skim is available.