... C-1 The purpose of this appendix is to provide an explanation of some of the tables and charts included as part of the Airport Cooperative Research Program (ACRP) 07-07 Guidebook for Evaluating Terminal Renewal versus Replacement Options.
From page 122...
... C-2 Guidebook for evaluating Terminal Renewal Versus Replacement Options Additional methods include ‘rules of thumb' measures developed on the basis of typical relationships between passenger and aircraft activity. Passenger and aircraft activity can be considered on an annual basis (often expressed as million annual passenger, or MAP)
From page 123...
... Analysis Templates C-3 4. Determine desired planning activity levels for the terminal renew and replace options and calculate passenger and aircraft activity statistics for these planning levels.
From page 124...
... C-4 Guidebook for evaluating Terminal Renewal Versus Replacement Options • Geographical location, and • Status of construction activity in the economy. Costs associated with construction and terminal operations phasing also need to be considered.
From page 125...
... Analysis Templates C-5 ing the appropriate balance of importance among the evaluation measures. Most qualitative measures can be rated in a good/better/best or poor/average/good range; for summary purposes, these ranges can be assigned values from 1 to 5, 1 to 10, or –2 to +2, etc.
From page 126...
... C-6 Guidebook for evaluating Terminal Renewal Versus Replacement Options C.4.1 Input Tab (Table C-5) The Project Funding Availability Input tab allows the user to input all of the required assumptions and to see the resulting effects on funding availability.
From page 127...
... Analysis Templates C-7 Project Assumptions 14. Project Impact on Non-airline Revenues -- The user enters the net impact of the terminal project on terminal non-airline revenues for the year the project becomes fully operational.
From page 128...
... C-8 Guidebook for evaluating Terminal Renewal Versus Replacement Options C.4.2 Output (Table C-6) The next tab of the template provides a table that presents the specified assumptions as well as the debt capacity, bond proceeds available for the project, and the total funds available for the project.