... 44 INTRODUCTION Over the years, a number of state transportation agencies (STAs) have utilized alternative contracting methods (ACMs)
From page 45...
... 45 Several methods have the potential to accelerate project completion, but there were not a sufficient number of responses to confirm this. These methods are • Early contractor involvement; • Construction manager at risk; • Design sequencing; and • Liquidated savings.