... 88 This appendix contains a consolidated list of handback criteria found in the content analysis of P3 concession agreements reviewed for this synthesis. The handback criteria are listed by project rather than consolidated to better associate them with the case examples found in Chapter 4.
From page 89...
... TxDOT Loop 375 HANDBACK REQUIREMENTS Asset Description Asset Sub SystemDescription Residual Life at Handback (Years) Handback Evaluation Tasks Handback Evaluation Criteria Flexible Pavement Pavement section within the project right-of-way.
From page 90...
... Signs and Beacons Single-post, multi-post, and overhead within the project right-of-way. 7 years Final inspection and reflectivity tests shall be conducted in accordance with the Maintenance Operations Manual within 120 calendar days before the end of the Term.
From page 91...
... Retaining Walls Within the project right-ofway. 20 years (retaining walls)
From page 92...
... Fencing Within the project right-ofway, all fencing along or within the project used to preserve a property boundary, control pedestrian and animal access, and maximize the safety and security of project users. 20 years Final inspection of all fencing shall be conducted within 90 calendar days before the end of the Term.
From page 93...
... NCTA I-77 HOT Lanes Table 23.3 - HANDBACK REQUIREMENTS Asset Description Asset Sub SystemDescription Residual Life at Handback (Years) Handback Evaluation Tasks Handback Evaluation Criteria Flexible Pavement Pavement section within the project right-of-way.
From page 94...
... Stripings and Markings Striping, markings, lettering, symbols within the project right-of-way. 2 years Inspect pavement markings/delineation in accordance with the Maintenance Operations Manual.
From page 95...
... High-Mast Light Poles Structural within the projectright-of-way. 15 years Final inspection, including x-rays of the lighting bases, shall be conducted within 180 calendar days before the end of the Term.
From page 96...
... Retaining Walls Within the project right-ofway. 20 years (retaining walls)
From page 97...
... FDOT I-595 Expressway TABLE 5.1 – HANDBACK REQUIREMENTS Asset Description Asset Sub System Description Life Remaining at Handback (Years) Handback Evaluation Tasks Handback Evaluation Criteria Asphalt Pavement Pavement section within N/A Concessionaire shall provide a Pavement Coring Plan for FDOT approval, and Concessionaire shall provide Pavement Cores with FDOT oversight Mill and resurface Category 1 Pavement, Category 2 Pavement, and Category 3 Pavement; shall be open to traffic a maximum of 10 years (120 months)
From page 98...
... High-Mast Light Poles Structural within the O&M Limits (Operating Period)
From page 99...
... CDOT US-36 Managed Lanes SCHEDULE 20 Handback Requirements Asset Description Asset Sub System Description Residual Life at Handback (years) Inspection Requirements Residual Life Methodology (RLM)
From page 100...
... Toll Collection Equipment Toll Collection Equipment 10 RLM shall draw on historical asset maintenance records, inspection, and test histories for each piece of equipment. Drainage Underground storm sewer 25 RLM shall draw on historical asset maintenance records, inspection, and test histories for each individual drainage asset.