Skip to main content

Currently Skimming:


Pages 1-29

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 1...
... 1   1.1 Introduction Prefabricated bridge elements and systems (PBES) offer significant time savings, cost savings, improved safety, and convenience for the traveling public.
From page 2...
... 2 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections bar spacing, bar detailing, type of reinforcement, ange thickness, and closure pour materials. Typical DBT girders connected by welded ties across grout-lled longitudinal joints are not performing well (French et al.
From page 3...
... Background 3   H (in.)
From page 4...
... 4 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections State transportation departments have also developed DBT sections. Washington state has developed a wide range of sections, including DBT girders, wide-flange thin-deck girders, and wideflange deck girders (WFDG)
From page 5...
... Background 5   Source: WSDOT 2016. Figure 1.4.
From page 6...
... 6 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections 2021. Tolerances of products are covered in Appendix B of the manual.
From page 7...
... Background 7   occur for girders in skewed bridges even if all members have the same camber profile, because the ends of the girders are offset by the skew distance. Though concrete overlays and composite decks have been used to smooth elevation differences caused by differential camber, this option defeats the purpose of accelerated bridge construction.
From page 8...
... 8 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections shrinkage does not induce tension and cause cracking at the interface of the girder and joint. However, magnesium phosphate-based patching grouts have been also investigated to take advantage of their rapid setting and early strength gain properties (Li et al.
From page 9...
... Background 9   This allows placement on decks with up to 10% slope. A fast-setting mix can also achieve 12 ksi compressive strength within 12 hours after placing.
From page 10...
... 10 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections The first use of UHPC for a bridge project in the United States was the Wapello County Bridge in Iowa. Constructed in 2005, the bridge consisted of a conventional concrete deck placed on top of three 110-ft.-long modified Iowa bulb tee sections made with UHPC.
From page 11...
... Background 11   strand capacity (270 ksi)
From page 12...
... 12 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections bars spaced along the joint, and (2) distributed reinforced joints.
From page 13...
... Background 13   These details required field welding and had a 5-in. width at the top.
From page 14...
... 14 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections details were investigated. One design used headed bar reinforcement with different lap lengths of 6, 4, and 2.5 in.
From page 15...
... Background 15   and (3) one moment-transferring connection that included lateral restraint of girder rotation.
From page 16...
... 16 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections Bridge Name or Route Feature Location Year SR 31 (Forgham Street) Canandaigua Outlet Lyons, NY 2009 Fingerboard Road Staten Island Expressway Staten Island, NY 2011 SR 248 Bennetts Creek Greenwood, NY 2011 SR 10 (Northampton Street)
From page 17...
... Background 17   UHPC longitudinal joints created the superstructure. The beams were 55 in.
From page 18...
... 18 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections lap splice.
From page 19...
... Background 19   localized cracking aer pullout tensile capacity of bers in the UHPC and yielding of the panel reinforcement had occurred. Overall, the behavior of the precast panel with transverse connection exceeded the behavior of the monolithic deck.
From page 20...
... 20 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections which included headed black bars and black straight bars. All specimens had a concave diamondshaped shear key with 6-in.
From page 21...
... Background 21   information is available about the performance of UHPC field connections. In addition to instrumentations installed on the bridge girders (Steinberg et al.
From page 22...
... 22 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections procedures assume grade 60 non-epoxy-coated reinforcement and a 22 ksi compressive strength for the UHPC in the joint. AASHTO criteria are limited to 15 ksi but were assumed to apply.
From page 23...
... Background 23   10-in. extension.
From page 24...
... 24 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections Two conditions are presented in the specifications to calculate the moment LLDFs. The first condition is used if the structure is sufficiently connected to act as a unit.
From page 25...
... Background 25   singe-lane and multilane conditions. The commentary to Article 4.6.2.2.1 states that the use of transverse mild steel rods secured by nuts or similar unstressed dowels should not be considered sufficient to achieve full transverse flexural continuity unless demonstrated by testing or experience.
From page 26...
... 26 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections (decked precast/prestressed concrete) girder bridges; new equations were therefore developed by Millam and Ma (2005)
From page 27...
... Background 27   diaphragms had lower LLDFs compared to a bridge with no diaphragms. However, increasing the number diaphragms to five had a minimal effect on the magnitude of the LLDF.
From page 28...
... 28 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections method, the cracks were determined to have completely penetrated one shear key at midspan and partially penetrated another shear key near the abutment. For these keys, when the bridge was subjected to a cyclic load, the initial cracks from the temperature effects propagated with no new cracks appearing due only to loading.
From page 29...
... Background 29   from top to bottom through the deck thickness and over the shear keys. It should be noted that no instrumentation was used to identify the causes for the cracks.

Key Terms



This material may be derived from roughly machine-read images, and so is provided only to facilitate research.
More information on Chapter Skim is available.