PROPOSAL/STUDY PLAN FOR A BRAB Date Prepared/Revised FEDERAL CONSTRUCTION COUNCIL PROJECT 5 May 1973 1 June 1974 20 June 1975 1. Title: Diesel Engine Criteria 2 June 1976 2.
|
From page 44... ...
7. Method of Carrying Out the Project: The project is being carried out as a technical study, with information being obtained through a survey of and conferences with manufacturers.
|
From page 45... ...
PROPOSAL/STUDY PLAN FOR A BRAB Date Prepured/Revised FEDERAL CONSTRUCTION COUNCIL PROJECT 5 May 1975 -- __1_ June 1974 20 1975 1. Title: Steam Boiler and Hot Water Generator Construction __2 June 1976 Criteria 2.
|
From page 47... ...
PROPOSAL/STUDY PLAN FOR A BRAB Date Preparcd/Revised FEDERAL CONSTRUCTION COUNCIL PROJECT 3 June 1976 1. Title: Formulation of R&D Office Space Assignment Criteria 2.
|
From page 49... ...
PROPOSAL/STUDY PLAN FOR A BRAB Date Prepared/Revised FEDERAL CONSTRUCTION COUNCIL PROJECT 10 May 1976 19 May 1976 2 June 1976 1. Title: ENERGY SURVEYS: THEIR NATURE AND COST 2.
|
From page 53... ...
FEDERAL CONSTRUCTION GUIDE SPECIFICATIONS Assignments and Status 29 September 1978 Indicated below, for each specification in the current FCGS master list, are the agency responsible for the development of the specification and the current status of the specification. The title codes in the status column have the following meaning: A: Specification published and available B: Draft specification ready for ballot or publication C: Draft specification being coordinated D: Draft specification being developed Rs: Revised version of a previously published specification on the same subject.
|
From page 54... ...
Current Responsible FCGS No. Title Agency Status 02250 Soil Treatment NAVFAC 02310 Foundation Piles GSA Cc 02310 Round Timber Piles NAVFAC Cc 02312 Prestressed Concrete Piling NAVFAC A 02315 Steel H-Beam Bearing Piles NAVFAC A 02317 Cast-in-Place Concrete Piles, Steel Casing NAVFAC A 02318 Auger-Placed Grout Piles NAVFAC A 02319 Round Timber and Concrete Composite Piles NAVFAC D 02325 Pressure-Injected Footings NAVFAC D 02351 Drilled Foundation Caissons (Piers)
|
From page 55... ...
Current Responsible FCGS No. Title Agency Status DIVISION 3 03300 Concrete (for Building Construction)
|
From page 56... ...
Current Responsible FCGS No. Title Agency Status DIVISION 7 07110 Membrane Waterproofing GSA RC 07120 Elastomeric Waterproofing System, Liquid Applied (Unexposed and Protected Membrane Systems)
|
From page 57... ...
Current Responsible FCGS No. Title Agency Status 08320 Metal-Clad Doors Unassigned Cc 08330 Coiling Door and Grilles Unassigned Cc 08360 Overhead Metal Doors | NAVFAC C 08361 Vertical Lift Metal Doors NAVFAC C 08371 Aluminum Sliding Glass Doors NAVFAC RC 08510 Steel Windows NAVFAC 08520 Aluminum Windows GSA A 08521 Hinged Aluminum Windows {Insulating Type with Venetian Blinds)
|
From page 58... ...
Current Responsible FCGS No. Title Agency Status 09910 Painting of Buildings (Field Painting)
|
From page 59... ...
Current Responsible FCGS No. Title Agency Status DIVISION 13 13410 Packaged Incinerators NAVFAC D 13451 Cold Storage Spaces OCE D 13500 Integrated Ceiling and Background ({ICB)
|
From page 61... ...
APPENDIX C MEMBERS of FEDERAL CONSTRUCTION COUNCIL STANDING COMMITTEES, TASK GROUPS, and INFORMAL PANELS (As of 30 September 1978)
|
From page 63... ...
Standing Committee on Architecture and Architectural Engineering James V Allred, Office of the Chief of Engineers James L
|
Key Terms
This material may be derived from roughly machine-read images, and so is provided only to facilitate research.
More
information on Chapter Skim is available.